The following work items will begin occurring for the Winthrop Beach project. You can expect to see these activities over the next two weeks.

Saugus
Install Erosion Controls
Clear and Grub Site
Strip and Screen soil
Construct Truck Entrance from Route 107

Crest Avenue
Site Preparation and Erosion Control
Excavation for parking lot extension

Winthrop Beach
Establish equipment storage area
Construct Beach access at Dolphin Avenue
Begin screening fence installation along seawall
Reconstruct Pearl Avenue revetment
Repair Groin#3 (opposite Wave Way Ave.)
Armor Stone Delivery

Questions or concerns about the project should be directed to DCR Resident Engineer Steve Colometo, at the DCR trailer behind the DCR bathhouse on Winthrop Shore Drive, by visit or phone (617-539-4957) during regular business hours, ~Monday through Friday from 7 a.m. – 3:30 p.m.~~ In case of an emergency, contact 911 or DCR’s 24/7 emergency hotline at the Massachusetts Emergency Management Agency at 508-820-1428.