Anticipated Work Schedule
Last Updated 3-29-10
Sewer Work
Walden Street/Pauline Street – 9/14/09 to 10-2-09
Putnam Street – Pauline to Jefferson – 10/5/09 to11-15-09
Putnam Place – 11-15-09 to 12-15-09
Putnam Street – Jefferson to Buchanan – 12-15-09 to 1-15-10
Services –4-1-10 to 5-1-10
Water Work
Fremont Street/Jefferson Street –4-15-10 to 5-15-10
Water Services – 5-15-10 to 6-1-10
Drain Work
Putnam Street 4-1-10 to 5-15-10
General Items
Construction Period – 9/8/09 to 10-15-10
Mobilization – 9/8/09 to 9/11/09
Winter Cleanup – 11/12/09 to 11/16/09
Final Paving – Fall 2010
|