Winthrop Center Area Roadwork Updates Beginning 4/24

Pleasant-Cottage Park-Somerset - Details Open Message for Details

Crew 1
4/24 to 4/28 the crew will continue to install main on Pleasant street.

Crew 2
4/24 to 4/28- The crew completed test holes on Cottage Park and will now continue with test holes on Somerset Ave. By the end of the week the crew will start installing main on Somerset Ave to Cottage Park, then down Cottage Park to Pleasant street. That may take us into the following week installing main on both Somerset Ave and Cottage Park.

Traffic patterns will be coordinated daily with the detail officers onsite.